‘Super sewer’ emergency back-up power project a success in London, UK

The existing sewer system in London, UK, built around 150 years ago, was originally constructed for a planned population growth of four million people. With London’s population now nearing the nine million mark, the city decided to invest in the Thames Tideway Tunnel, dubbed London’s new ‘super sewer’.

The Ferrovial Agroman/Laing O’Rourke Joint Venture (FLO JV) was selected to build the central section of the new 25km Thames Tideway Tunnel to run under the River Thames. As part of this landmark project, Ampcontrol was contracted to assist with the provision of emergency back-up power.

Ampcontrol provided 1,100kVA of emergency back-up generation capacity and the associated cabling for the tie-in to the distribution system of the project.

Due to the project’s time sensitivity, temporary generators of equal capacity were supplied during the manufacturing period of the new units. Ampcontrol also provided onsite pre-commissioning support to ensure smooth installation and operational readiness of the new units supplied.

Ampcontrol is proud to have successfully completed the scope of generation capacity supply and support within the required timeframe to one of the most significant UK tunnelling projects in the heart of London.

Steven Edmund, Ampcontrol’s Managing Director in the UK, said, “A very high standard of quality is demanded by the UK industry and in true Ampcontrol style this was achieved by following sound engineering principles, providing high quality equipment, being customer centric, and recognising the requirements of all stakeholders and the environment.”

Read our Thames Tideway Tunnel case study here.

Take a deep dive into AS/NZS 2290.3:2018

Ampcontrol’s Group Engineering Manager, Ian Webster, as a presenter for Verico Training Services, will be facilitating at a new series of seminars around Australia. At the seminars, which are designed for key stakeholders in the coal mining sector, Ian will discuss how to interpret and comply with the new edition of the AS/NZS 2290.3:2018 Standard.

Not only is Ian one of Australia’s leading technical experts in the design, performance and maintenance of gas detectors for use in coal mines, he has provided significant input into the development of national and international standards for gas detection in mines. Ian has presented invited papers on the subject at a host of leading industry conferences, including the Queensland Mines Health and Safety Conference, the Electrical Engineering Safety Seminar and the Mine Managers Association of Australia.

Ian is also Chief Researcher for an ACARP project looking into dust accumulation in gas detectors and the effect this has on detector performance.

In this deep review, participants will develop a comprehensive understanding of requirements and recommendations for the inspection and maintenance of gas detection equipment. Find out more or register now so you have the information you need to check in on your mine’s current procedures for the facilitation of safe, efficient and productive use of gas detection and monitoring equipment.

Ampcontrol Heads to the 2019 NT Resources Week

Ampcontrol is proud to be a Supporting Sponsor at the 2019 NT Resources Week, held at the Darwin Convention Centre from 4 – 5 September.

Held in partnership with the Northern Territory Government, NT Resources Week combines three conferences; South East Asia Australia Offshore and Onshore Conference; Mining the Territory; and Environmental Management & Logistics Forum.

You’ll find Ampcontrol on stand 31 in the Mining The Territory exhibition hall where our team members will be on hand to discuss our range of offerings, from HV field service and rapidly deployable energy infrastructure solutions through to our newest off grid containerised water filtering unit, Gilghi.

For more information and to view the full program, head to the NT Resources Week website.

Related Case Studies

Case Study: Bladin Point LNG Processing Facilities


Case Study: Channel Island Power Station Upgrade


Case Study: McArthur River Mine